Lifting Operations

Lifting Operations Permits: LOLER 1998, Lift Plans & Appointed Person Duties

May 2026 · 9 min read · PermitDesk

Lifting operations are among the most heavily regulated activities on UK construction and industrial sites — and for good reason. Crane and hoist failures, dropped loads, and equipment overturns cause fatalities and serious injuries every year. The consequences of getting it wrong are immediate and unforgiving.

The Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) impose specific legal duties on every dutyholder involved in a lifting operation — from the equipment owner to the operator to the person directing the lift. A lifting operations permit to work is the document that brings all of those duties together before the first lift takes place.

This guide covers what LOLER requires, the role of the Appointed Person, what a lifting permit must include, and the mistakes that lead to incidents.

The legal framework: LOLER 1998

LOLER applies to any lifting equipment used at work and any lifting operation carried out using that equipment. It requires that:

LOLER and PUWER together: LOLER works alongside the Provision and Use of Work Equipment Regulations 1998 (PUWER), which governs the maintenance, inspection, and general safe use of all work equipment. Lifting equipment must satisfy both sets of regulations.

Relevant industry standards include BS 7121 (Safe Use of Cranes), LEEA guidance on lifting accessories, and IPAF guidance for MEWPs and personnel-carrying equipment.

What equipment requires a lifting operations permit?

A permit to work is expected wherever a lifting operation creates a foreseeable risk of injury to persons. In practice, this includes:

Equipment typeWhen a permit applies
Mobile cranesAll operations — complex lift plan required for loads over 1 tonne or where persons may be in the load path
Tower cranesAll lifts, particularly where load path crosses public areas or other work zones
Telehandlers and rough-terrain forkliftsWhere used for lifting (not just moving) loads, particularly at height
Chain hoists and gantry cranesWhere the load is suspended over areas where persons may be present
MEWPs used as lifting devicesWhere the platform carries loads (not just persons) — note: MEWP use for access alone is a Working at Height issue, not a lifting operation
Tandem / multi-crane liftsAlways require a formal permit and a specific engineering lift plan

The Appointed Person: role and responsibilities

LOLER's requirement that lifting operations be "planned by a competent person" is the legal basis for the Appointed Person (AP) role. The AP is responsible for planning the lift and ensuring it is carried out safely.

The AP must have the competence — through a combination of training, knowledge, and experience — to:

The Appointed Person must sign the permit before any lift takes place. A permit that has been issued without the AP's signature — even if a competent operator is present — does not satisfy LOLER's planning requirement. This is a common inspection finding and a common cause of enforcement action.

The AP role is distinct from the crane operator. The operator carries out the lift; the AP plans it and confirms it is safe to proceed. On a straightforward, routine lift these may sometimes be the same experienced individual on smaller sites — but for complex lifts, the AP should always be independent of the operating team.

Lift plans: what they must cover

Every lifting operation must be planned, and the plan must be documented. A basic lift plan should cover:

For complex lifts — tandem picks, lifts near power lines, lifts over occupied areas — the lift plan should be an engineered document, reviewed and signed by a chartered or suitably qualified engineer.

LOLER examination records: what to check

LOLER requires that lifting equipment and all lifting accessories are thoroughly examined by a competent person at specified intervals:

Equipment typeExamination interval
Equipment used to lift persons (e.g. MEWP baskets, cradles)Every 6 months
Lifting accessories (slings, chains, shackles, hooks)Every 6 months
Other lifting equipment (cranes, hoists, telehandlers)Every 12 months
Following exceptional circumstances (damage, malfunction, major alteration)Before next use

The permit issuer must confirm that current LOLER thorough examination certificates are on site and within date for all equipment and accessories to be used. An out-of-date certificate is grounds to stop the lift — regardless of how recently the equipment was last used.

What a lifting operations permit must include

Lifting Operations Pre-Authorisation Checks

Overhead power line clearances

Overhead power lines are a specific and serious hazard for crane operations. The statutory safe approach distances under the HSE's Electricity at Work guidance are a minimum — most site rules and insurance requirements impose greater clearances. The permit must record that overhead lines have been identified, that their voltage has been confirmed (which determines the safe approach distance), and that the operator has been briefed on the clearance requirement.

Ground conditions and outrigger mats

A mobile crane that overturns because of inadequate ground support is as dangerous as a dropped load. The AP must assess the ground bearing capacity at the crane position, specify outrigger mat size and type accordingly, and confirm that the mats have been correctly positioned before the crane is set up for the lift. This must be recorded on the permit — not assumed.

Exclusion zones

No person should be in the load path during a lift — not walking past, not working nearby, not standing at the pick or landing point. The exclusion zone must be established before the lift commences, physically demarcated with barriers or tape, and maintained continuously throughout the lift. The permit must record who is responsible for clearing and maintaining the zone.

Wind speed

Every crane and MEWP has a maximum rated wind speed — typically expressed in metres per second or on the Beaufort scale. The permit must record the limit for the equipment in use, confirm that wind speed has been checked before the lift, and state the action to be taken if wind speed exceeds the limit during a lift (typically: suspend the load in a safe position if possible, and abort).

Common mistakes to avoid

Download a free lifting operations permit template

We've produced a free Lifting Operations Permit to Work template in Word (.docx) format, available in both a pre-filled version (standard hazards and controls already populated) and a blank version.

Lifting Operations Permit to Work — Free Template

Covers LOLER 1998 and BS 7121 requirements. Pre-filled with standard hazards, controls, and pre-authorisation checks including Appointed Person sign-off. Editable Word (.docx) format.

For all permit types — including Excavation, Hot Works, and more — visit the templates page.

Beyond paper: managing lifting permits digitally

Lifting operations require precise record-keeping: the Appointed Person's sign-off, the certificate numbers and expiry dates, the wind speed at time of lift, the exclusion zone confirmation. On paper, these records are scattered across forms, site diaries, and cab paperwork that is easy to lose and difficult to retrieve.

PermitDesk generates lifting permits and all other PTW types digitally — with the AP sign-off captured as a named digital signature, certificate numbers recorded against the permit, and a full timestamped audit trail automatically stored. When LOLER records are requested following an incident, you can produce them in seconds.

Issue your first lifting permit in under 2 minutes

PermitDesk handles the drafting. The Appointed Person signs off digitally. Full LOLER audit trail included.

Start your free 14-day trial

Related reading

What is a permit to work? A plain-English guide

Excavation & Ground Works Permits: CDM 2015 guide

Hot Works Permits: a complete guide for site managers

Browse all free permit to work templates